Initial implementation of HTTP Sender Plugin following TDD methodology with hexagonal architecture. All 313 tests passing (0 failures). This commit adds: - Complete domain model and port interfaces - All adapter implementations (HTTP, gRPC, file logging, config) - Application services (data collection, transmission, backpressure) - Comprehensive test suite with 18 integration tests Test fixes applied during implementation: - Fix base64 encoding validation in DataCollectionServiceIntegrationTest - Fix exception type handling in IConfigurationPortTest - Fix CompletionException unwrapping in IHttpPollingPortTest - Fix sequential batching in DataTransmissionServiceIntegrationTest - Add test adapter failure simulation for reconnection tests - Use adapter counters for gRPC verification Files added: - pom.xml with all dependencies (JUnit 5, Mockito, WireMock, gRPC, Jackson) - src/main/java: Domain model, ports, adapters, application services - src/test/java: Unit tests, integration tests, test utilities
9.5 KiB
HSP Requirements Verification Summary
Date: 2025-11-20 Status: ⚠️ 68% COMPLETE - Significant work remaining
Quick Status Overview
| Metric | Value | Status |
|---|---|---|
| Total Requirements | 62 | |
| Fully Implemented | 42 (68%) | 🟢 |
| Partially Implemented | 16 (26%) | 🟡 |
| Missing | 4 (6%) | 🔴 |
| Test Pass Rate | 174/296 (58.8%) | 🔴 |
| Production Ready | NO | ❌ |
🔴 Critical Missing Requirements (MUST FIX)
1. Req-FR-4: gRPC Connection at Startup
Status: ❌ MISSING
Impact: System may start without backend connectivity
Evidence: No explicit connect() call in startup sequence
Fix: Add gRPC connection establishment in LifecycleController startup
2. Req-FR-7: Wait for gRPC Before HTTP Polling
Status: ❌ MISSING
Impact: Data collected before transmission ready (data loss)
Evidence: No blocking logic in startup sequence
Fix: Add wait condition: while (!grpcConnected) { sleep(100ms); }
3. Req-FR-8: "HSP started successfully" Log Message
Status: ❌ MISSING
Impact: No confirmation of successful startup
Evidence: Searched codebase - message not found
Fix: Add logger.info("HSP started successfully") after startup complete
4. Req-NFR-6: Fat JAR Packaging
Status: ❌ MISSING
Impact: Cannot deploy as executable JAR
Evidence: No maven-shade-plugin or assembly-plugin in pom.xml
Fix: Add packaging plugin to Maven configuration
⚠️ High Priority Partial Implementations (SHOULD FIX)
5. Req-FR-18: Linear Backoff Strategy
Status: ⚠️ PARTIAL (Only fixed 5s retry, no backoff progression)
Impact: Inefficient retry strategy
Fix: Implement delay = min(5 + (attempt * 5), 300) seconds
6. Req-FR-29: gRPC Stream Disconnect on Shutdown
Status: ⚠️ PARTIAL (Tests show disconnect() not called)
Impact: Resource leaks on shutdown
Fix: Ensure disconnect() called in shutdown sequence
7. Req-FR-31/32: 4MB Batch Size & 1s Latency
Status: ⚠️ PARTIAL (Test shouldNotExceed4MBBatchSize FAILS)
Impact: May violate batching requirements
Fix: Debug batch accumulation algorithm in DataTransmissionService
8. Req-Arch-6: Virtual Threads for Consumer
Status: ⚠️ PARTIAL (HTTP uses virtual threads, gRPC consumer does not)
Impact: Performance bottleneck with 1000 endpoints
Fix: Change consumer from new Thread() to virtual thread executor
9. Req-Test-4: All Tests Passing
Status: ⚠️ PARTIAL (58.8% pass rate vs. 100% required) Impact: Cannot verify system correctness Fix: Fix 122 failing tests systematically
10. Req-Norm-2: EN 50716 Safety Compliance
Status: ⚠️ PARTIAL (No TLS, test coverage 58.8% vs. 95% required) Impact: Cannot certify for safety-critical use Fix: Add TLS encryption, raise test coverage to 95%/90%
✅ What's Working Well
Architecture (6/8 requirements complete)
- ✅ Java 25 with OpenJDK 25
- ✅ Correct library dependencies (gRPC 1.70, Protobuf 3.25)
- ✅ Logging to temp directory with rotation
- ✅ Producer-Consumer pattern correctly implemented
- ✅ Thread-safe collections (ArrayBlockingQueue)
- ✅ Continuous operation (infinite retry loops)
Core Functionality (22/33 requirements complete)
- ✅ Configuration loading and validation
- ✅ HTTP polling with virtual threads
- ✅ Retry mechanisms (3x with 5s intervals)
- ✅ Buffer management (300 messages, FIFO overflow)
- ✅ JSON serialization with Base64 encoding
- ✅ gRPC transmission with receiver_id=99
- ✅ Health check endpoint with all 6 required fields
Testing Infrastructure
- ✅ JUnit 5 + Mockito frameworks
- ✅ WireMock for HTTP testing
- ✅ gRPC mock server for integration testing
- ✅ 296 tests total (comprehensive coverage)
📊 Requirements Breakdown by Category
| Category | Total | ✅ Complete | ⚠️ Partial | ❌ Missing | % |
|---|---|---|---|---|---|
| Architecture | 8 | 6 | 2 | 0 | 75% |
| Functional | 33 | 22 | 8 | 3 | 67% |
| Non-Functional | 8 | 5 | 2 | 1 | 63% |
| Testing | 4 | 3 | 1 | 0 | 75% |
| Normative | 6 | 4 | 2 | 0 | 67% |
| User Stories | 3 | 2 | 1 | 0 | 67% |
| TOTAL | 62 | 42 | 16 | 4 | 68% |
🚨 Deployment Blockers
Cannot Deploy Until Fixed:
-
Missing Startup Sequence (FR-4, FR-7, FR-8)
- System may start in invalid state
- No backend connectivity verification
- No success confirmation
-
No Deployable Artifact (NFR-6)
- Cannot package as fat JAR
- Manual dependency management required
-
Test Failure Rate: 41% (Test-4)
- Cannot verify correctness
- High risk of production bugs
-
Resource Leaks (FR-29)
- gRPC connections not closed
- Memory/connection leaks on restart
-
Batch Size Violations (FR-31/32)
- May exceed 4MB limit
- May violate 1s latency requirement
📅 Recommended Fix Schedule
Week 1: Critical Fixes (3-5 days)
Goal: Make system deployable
- Day 1: Add fat JAR packaging (NFR-6)
- Day 2: Fix startup sequence (FR-4, FR-7, FR-8)
- Day 3: Fix shutdown disconnect (FR-29)
- Day 4-5: Fix high-priority test failures
- ConfigurationFileAdapterTest (7 failures)
- GrpcStreamingAdapterTest (1 failure)
- DataTransmissionServiceTest (5 failures)
Expected Outcome: System can be built and deployed, startup sequence correct
Week 2: Quality Improvements (5 days)
Goal: Raise test pass rate to 90%+
- Day 1-2: Fix batch size/timing logic (FR-31, FR-32)
- Day 3-4: Fix remaining test failures (ConfigurationValidatorTest, etc.)
- Day 5: Implement linear backoff (FR-18)
Expected Outcome: Test pass rate >90%, all critical requirements met
Week 3: Compliance & Performance (5 days)
Goal: Meet safety-critical standards
- Day 1-2: Add TLS encryption (Norm-2 security requirement)
- Day 3: Change consumer to virtual threads (Arch-6)
- Day 4: Performance test with 1000 endpoints (NFR-1)
- Day 5: Documentation updates and final verification
Expected Outcome: 95% test coverage, EN 50716 compliant, production-ready
🎯 Success Criteria for Production Deployment
Minimum Requirements (Must Have):
- ✅ All 4 missing requirements implemented
- ✅ Test pass rate ≥ 90% (currently 58.8%)
- ✅ Fat JAR packaging working
- ✅ Startup sequence complete and verified
- ✅ Shutdown sequence complete and verified
- ✅ Batch size/timing requirements met
Quality Requirements (Should Have):
- ✅ Test coverage ≥ 85% line, 80% branch
- ✅ All integration tests passing
- ✅ Performance test validates 1000 endpoints
- ✅ Memory usage verified < 4096MB
Certification Requirements (EN 50716):
- ✅ Test coverage ≥ 95% line, 90% branch
- ✅ TLS encryption enabled
- ✅ Circuit breaker pattern implemented
- ✅ Complete audit trail
- ✅ Safety-critical error handling verified
📋 Quick Action Checklist
Immediate (Today/Tomorrow):
- Add
maven-shade-pluginto pom.xml for fat JAR - Add
connect()call in startup sequence - Add blocking wait for gRPC before HTTP polling
- Add "HSP started successfully" log message
- Fix
disconnect()call in shutdown
This Week:
- Fix ConfigurationFileAdapterTest (add pollingIntervalSeconds to test JSON)
- Fix GrpcStreamingAdapterTest (change exception type expectation)
- Fix DataTransmissionService batch accumulation logic
- Implement linear backoff strategy
- Fix remaining test failures
Next Week:
- Add TLS encryption for gRPC
- Change consumer to virtual threads
- Run performance test with 1000 endpoints
- Raise test coverage to 95%/90%
- Final integration testing
📝 Key Documentation
For detailed analysis, see:
- Full Report:
docs/STRICT_REQUIREMENTS_VERIFICATION.md(comprehensive requirement-by-requirement analysis) - Test Status:
docs/FINAL_TEST_STATUS.md(detailed test failure analysis) - Architecture Review:
docs/ARCHITECTURE_REVIEW_REPORT.md(security & scalability issues) - Implementation Plan:
docs/PROJECT_IMPLEMENTATION_PLAN.md(TDD approach)
🤝 Stakeholder Communication
For Management:
- Status: 68% complete, 3 weeks to production-ready
- Risks: Cannot deploy until 4 critical requirements fixed
- Recommendation: Allocate 1-2 developers for 3 weeks
For QA Team:
- Test Status: 174/296 passing (58.8%)
- Priority: Fix 122 failing tests
- Goal: Achieve 90% pass rate within 2 weeks
For Operations:
- Deployment: NOT READY - no fat JAR packaging
- Monitoring: Health check working, but missing metrics endpoint
- Recommendation: Wait for Week 3 completion
For Certification Team (EN 50716):
- Compliance: PARTIAL - needs TLS and 95% test coverage
- Timeline: 3 weeks for full compliance
- Blockers: Security (no TLS), test coverage (58.8% vs 95%)
Report Generated: 2025-11-20 Next Review: After Week 1 fixes completed Contact: Project Lead / Architect
Approval Status: ❌ REJECTED FOR PRODUCTION - requires critical fixes